Case Study: Klargester Sewage Treatment Plant Installation in Suffolk
At Cargate Engineering Ltd, we specialise in the installation of Klargester Bio-Disc Sewage Treatment Plants for domestic and commercial properties across Suffolk, Norfolk, Cambridgeshire and the surrounding areas. As an approved Klargester installer, we provide a complete turnkey solution, from the initial site survey through to excavation, installation, commissioning, and final reinstatement.
This recent project involved replacing an ageing Septic Tank with a Klargester NF Bio-Disc Gravity Sewage Treatment Plant, providing the property owner with a reliable, environmentally compliant wastewater solution for years to come.
The Client’s Challenge
The customer contacted Cargate Engineering Ltd to replace a Victorian septic tank, believed to have been constructed in the 1800s, which was discharging untreated effluent into a nearby ditch.
As the existing system no longer met current environmental standards and was discharging illegally, a replacement Sewage Treatment Plant was required to bring the property into compliance and provide a reliable, long-term wastewater treatment system.
Our Solution
Following a detailed site assessment, our experienced team designed an installation that met both the property’s requirements and the EA general binding rules.
The project included:
- Site survey and installation design.
- Removal and decommissioning of the existing septic tank.
- Installation of a new Klargester NF Bio-Disc Gravity Sewage Treatment Plant.
- Installation of 150 metres of replacement inlet and outlet pipework.
- Electrical connection and commissioning.
Full testing of the system. - Backfilling and reinstatement of the surrounding ground.
Throughout the installation, our team worked carefully to minimise disruption to the client, taking into consideration the sensitive nature of the site as a working horse stud. Works were planned and carried out with the utmost care to ensure the safety and wellbeing of both the horses and staff, while maintaining the highest standards of workmanship, health and safety throughout the project.
Why our client chose a Klargester System
When recommending a Sewage Treatment Plant solution, our preferred choice is always a Klargester Bio-Disc system. As an approved Klargester installer, we know first-hand the quality, reliability and long-term performance these systems provide, making them an excellent investment for our client.
Klargester is recognised throughout the UK as a leading manufacturer of wastewater treatment solutions, with a reputation for innovation, durability, and efficient performance. Designed to provide effective treatment of domestic wastewater, Klargester systems offer a dependable, long-term solution for properties that are not connected to the mains sewer network.
Key benefits of a Klargester sewage treatment plant include:
- Reliable and efficient wastewater treatment.
- Robust, durable construction designed for a long service life.
- Suitable for both new-build developments and replacement installations.
- Low maintenance requirements when serviced in accordance with the manufacturer’s recommendations.
- Quiet, energy-efficient operation.
- Available in a range of sizes to suit domestic and commercial applications.
By choosing a Klargester system installed by Cargate Engineering Ltd, you can be confident that your wastewater treatment solution has been designed, installed and commissioned to the highest standards by an approved Klargester installer.
Why Choose Cargate Engineering?
Choosing an approved Klargester installer means your project is carried out by experienced professionals who understand every aspect of Sewage Treatment Plant installation.
At Cargate Engineering Ltd, we offer:
- Approved Klargester installations.
- Complete project management.
- Experienced team with over 30 years of experience in the industry.
- Domestic and commercial Sewage Treatment Plant installations.
- In house servicing and maintenance.
- Honest advice and transparent quotations.
Whether you’re replacing an ageing septic tank or installing a new sewage treatment plant for a self-build or commercial development, our team can deliver a professional solution tailored to your requirements.
Please contact Cargate Engineering Ltd to arrange a site survey and receive expert advice. We’ll assess your property, recommend the most suitable solution, and provide a detailed, no-obligation quotation.
Please click here to view our Klargester Approved Installer Certificate.